|
UNDERGROUND The
cost for underground service depends on the extent of special engineering
required. The least complicated and cheapest situation is if a padmount
transformer, stubout, or access hole is already on the property. If this
is the case, engineering may not be required. The customer simply installs
the service entrance equipment, has it inspected, and calls the utility to
have service connected.
The customer is responsible for providing,
installing, and maintaining all equipment from the point of delivery
except for the meter.
The
power company is responsible for providing and installing the meter,
completing the connections between the meter and the service conductors,
and making the final connections at the point of delivery. If CTs are
being used, the utility also provides the CTs and makes the connections to
them and to the meter.
CHECK LIST FOR INSTALLING UNDERGROUND
SERVICE
To
obtain new underground electric service, the customer:: 1.
Contacts the utility to discuss the project, to determine where the
service will originate from and the point of delivery, and to request the service. 2. If
requested, provides the utility with: ▪
Site drawings ▪ Load
information ▪ An easement for
permanent equipment owned by the power company and installed on the customer's
property ▪ Payment for pre-construction
costs 3. Obtains an electrical work permit from the
inspecting agency. 4. Selects the type meter that fits the
situation. There are three options: ▪
Surface-mount meter ▪ Flush-mount
meter ▪ Pedestal-mount meter
5. Installs the service equipment. 6. Calls the locating
service ("Call Before You Dig") to locate any existing underground wires,
cables, and pipes. 7. Obtains an electrical
inspection. 8. Contacts the utility.
Then the
utility: 1. Installs the meter in the
socket. 2. If CTs are being used, installs the CTs and
completes the wiring between the CTs, the meter, and the service lines. 3. Connects the
conductors at the point of delivery.
LOCATING UNDERGROUND
UTILITIES
The customer must call the underground utilities locating service at
least two full working days (48 hours) before trenching or excavating for
underground service. One call to the locating service notifies all
utilities that locates are required. In some areas, not all utilities are
members of the one-call system. In those areas, the customer must contact
each utility individually.
Excavation must not begin until the
locations of underground wires, cables, and pipes have been marked, or the
utilities have informed the customer that they have no facilities in the
area.
Any digging within 24 inches of location marks must be done
by hand.
The
color code for marking underground utilities is:
-----------------------------------------------------------
Color
Underground
Service ----------------------------------------------------------- !
Red
Electric !
Yellow Gas,
Oil, Steam !
Orange Telephone,
Cable TV !
Blue
Water
!
Purple Reclaimed
water !
Green Sewer
!
Pink
Temporary
survey marks '
White Proposed excavation
-----------------------------------------------------------
Transformer
Installations
Underground
Service, Surface-Mount Meter
Underground Service,
Meter Post
Underground
Service, Pedestal Meter |